Joined
·
6,781 Posts
I just got done with the rough in with all that cast iron. I transitioned to PVC right at the traps. The GC had built a 4 foot high wall at the end of the tub. We went in and set the tub and perfecto! The W&O dropped right into our rough in pipes! Perfect! We buttoned it up and my partner said "You know, with all the troubles here with the HO and GC maybe we should just sit the tub in and wait". I said no, where else can the tub go? We get done, I call the HO to see where she wants the body sprayers for her shower to be installed when she told us the GC forgot to make a 6" ledge on all 4 sides of the tub!
Now we must go back on Sunday to remove the tub, build the wall for the GC, then re run the drain!
Oh well, someone is gonna pay because as the HO said, we did it the way the plans said, but the GC did not tell us there was a change.
Now we must go back on Sunday to remove the tub, build the wall for the GC, then re run the drain!
Oh well, someone is gonna pay because as the HO said, we did it the way the plans said, but the GC did not tell us there was a change.